Mirasol 01

Mirasol

Project Info Mirasol Summary of Project: 600 sqft detached ADU w/120 sqft concrete patio deck Two bedroom, one bathroom with great room and kitchen blended Budget: Materials & Labor: $291,000 Plans: $8,700 Permits: $7,650 Time for completion: Plan & Engineering: 30 Days Permits: 60 Days Grading:  3 Days Construction: Est. 3 Months Previous Next Mirasol …

Mirasol Read More »

Upland front

Upland

Project Info Upland Summary of Project: 1,029 sqft detached ADU . Two bedroom, two bathroom with great room and kitchen blended Budget: Materials & Labor: $291,000 Time for completion: Plan & Engineering : 30 Days Grading :  3 Days Construction: Est. 4 Months Previous Next Los Angeles

La Verne

La Verne

Project Info La Verne Summary of Project: 1,029 sqft detached ADU . Two bedroom, two bathroom with great room and kitchen blended Budget: Materials & Labor: $291,000 Time for completion: Plan & Engineering : 30 Days Grading :  3 Days Construction: Est. 4 Months Previous Next Los Angeles

La Habra

La Habra

Project Info La Habra Summary of Project: 1,029 sqft detached ADU . Two bedroom, two bathroom with great room and kitchen blended Budget: Materials & Labor: $291,000 Time for completion: Plan & Engineering : 30 Days Grading :  3 Days Construction: Est. 4 Months Previous Next Los Angeles

upland 2

Upland 2

Project Info Upland 2 Summary of Project: 1,029 sqft detached ADU . Two bedroom, two bathroom with great room and kitchen blended Budget: Materials & Labor: $291,000 Time for completion: Plan & Engineering : 30 Days Grading :  3 Days Construction: Est. 4 Months Previous Next Los Angeles

Springdale LA

Springdale LA

Project Info Springdale LA Summary of Project: 1,029 sqft detached ADU . Two bedroom, two bathroom with great room and kitchen blended Budget: Materials & Labor: $291,000 Time for completion: Plan & Engineering : 30 Days Grading :  3 Days Construction: Est. 4 Months Previous Next Los Angeles

Los Angeles 03

Los Angeles

Project Info Los Angeles Summary of Project: 1,029 sqft detached ADU . Two bedroom, two bathroom with great room and kitchen blended Budget: Materials & Labor: $291,000 Time for completion: Plan & Engineering : 30 Days Grading :  3 Days Construction: Est. 4 Months Previous Next Los Angeles Los Angeles Los Angeles Los Angeles Los …

Los Angeles Read More »

Torrance 08

Torrance

Project Info Torrance Summary of Project: 1,029 sqft detached ADU . Two bedroom, two bathroom with great room and kitchen blended Budget: Materials & Labor: $291,000 Time for completion: Plan & Engineering : 30 Days Grading :  3 Days Construction: Est. 4 Months Previous Next Torrance Torrance Torrance Torrance Torrance Torrance Torrance Torrance Torrance Torrance …

Torrance Read More »

Garden Grove 01

Cypress

Project Info CYPRESS Summary of Project: 1,029 sqft detached ADU . Two bedroom, two bathroom with great room and kitchen blended Budget: Materials & Labor: $291,000 Time for completion: Plan & Engineering : 30 Days Grading :  3 Days Construction: Est. 4 Months https://www.youtube.com/watch?v=2_Qlg_xzSEk&list=PLfRCdYZ6gzH0Ukc8xjJn32xJwSzzwflAh Previous Next Cypress Cypress Cypress Cypress Cypress Cypress Cypress Cypress Cypress …

Cypress Read More »

Springoak LA 01

Spring Oak

Project Info Spring oak Summary of Project: The house was completely demolished and rebuilt with the exception of the basement. The home was purchased to build a high-end Airbnb. The original home was 1,554 sqft, after construction was completed it was 3,300 sqft 3 story. Budget: Materials & Labor: $1,735,000 Time for completion: Plans & …

Spring Oak Read More »