Spring oak

Summary of Project:

  • The house was completely demolished and rebuilt with the exception of the basement.
  • The home was purchased to build a high-end Airbnb.
  • The original home was 1,554 sqft, after construction was completed it was 3,300 sqft 3 story.

Budget:

  • Materials & Labor: $1,735,000

Time for completion:

  • Plans & Engineering :  2 months
  • City Approval : 5 months
  • Demolition and removal : 35 Days
  • Construction:  8 Month